In 2026, the company established a specialized Large Seamless Pipe Division at Unit-3 in Mandali, adding an 18,000 MTPA capacity to produce precision-engineered, 6 to 40-inch OD pipes for the power and heavy engineering sectors.
This milestone was fortified by a strategic raw material MoU and the integration of advanced turning, peeling, and 32-probe Ultrasonic Testing technologies to guarantee strict IBR compliance.
Installed a 120-ton cold draw bench, pointing/swaging machine, 100 MTPD furnace, and Shot Blasting line at Unit-3 for heavy wall tube production.
UT machines of all three units were upgraded to meet the ever-evolving stringent customer requirements.
Installed a 160-ton cold draw bench with induction pointing machine at Unit-2 and commissioned an additional heavy pilger machine at Unit-1 (SS Division).